1. Meet with the Client
a. Discuss Client needs such as type of home,
location of lot etc…
b. Review Client plans and make suggestions if
needed.
c. Answer any questions the Client may have.
2. Do all preliminary work
a. Obtain Surveys, Elevation Certificates and
Plot Maps.
b. Obtain necessary Permits, CAMA, Zoning,
Floodplain Development and Building.
c. Get preliminary field work done, lot cleared
and prepped, driveway built, etc…
3. Piling installation
a. All pilings used are pressure treated with a
diameter of 8x8 inches and the length is
determined by a professional structural
engineer.
b. All pilings are installed to a depth
pre-determined by the engineer. Most are at
least 15 feet deep. This is dependent on the
location of the lot.
4. Banding
a. All Banding material is manufactured
micro-lams sized by the engineer.
b. The pilings are notched to allow for the
micro-lams to set on top of them and then be
bolted in place using 5/8in galvanized bolts and
banding straps.
5. Framing
a. Floor trusses are then installed. The floor
trusses are scissor type to allow for easy
installation of plumbing, electrical and HVAC
components and are pre-sized by the engineer.
b. Sub-flooring is then installed. The product
that we use is known in the industry as the
Advantech type. It is made from wood chips that
have been treated with a product such as
Thompson's Water Seal. The chips are then glued,
and mechanically pressed together. This product
comes with a 50 year warrantee.
c. Exterior wall framing. All the exterior walls
are framed with 2x6 studs. This makes the walls
1/3 stronger and thicker than what most
contractors use. This extra thickness also
allows for a thicker insulation to be installed
which saves you money on your heat and
air-conditioning bills.
d. Exterior wall sheathing is then applied over
the 2x6 studs. We first apply a vertical layer
of ½ inch thick OSB wall board that is nailed
every 3 inches around the edges and every 6
inches in the middle. We then horizontally apply
a ½ inch layer of Advantech (similar to what we
use on the sub-flooring and comes with a 30 year
warranty) which is nailed the same way as the
first layer. This gives us a full 1 inch of
sheathing and makes our exterior walls almost
twice as strong as other contractors.
e. The exterior sheathing is then covered with
30 pound asphalt paper which is well known for
its durability.
f. Roof framing is dependent on the plans and
the style of the home. Usually it is done with
scissor trusses. Sometimes the roof is hand
framed to allow for the extra high vaulted
ceilings.
g. After the roof is framed the sheathing is
installed, again using the Advantech product
with the 30 year warranty. After the Advantech
sheathing is applied we install a product known
as weathergard. It is a rubber membrane that is
applied to the entire roof. This product has one
side that is very sticky and when it bonds to
the sheathing it is very difficult to remove it.
After that either shingles or metal roofing is
applied per the client's choice
6. Windows & Doors
a. We use two types of windows and doors. The
choice is determined by the client's budget. Our
preference is to use the more expensive one
which is the Anderson 400 Series with the Impact
Resistant Glass. Our other choice is the
CertainTeed Vinyl windows which are manufactured
by Viwinco. These are also available with the
impact resistant glass.
b. Before the windows & doors are installed the
openings are prepped using the weathergard
membrane to protect the wood from any moisture
that might penetrate the siding.
c. A layer of caulk is then applied to the area
and the window is installed using galvanized
nails, nailed through the nailing flanges.
d. Window tape is then applied to all the edges
of the windows and doors.
7. Siding
a. The siding is then applied. We normally use
Hardi-plank siding which is a concrete product.
This product is very durable. It comes
pre-painted to any color that the client
chooses. It is blind nailed using galvanized
nails with the exception of using stainless
steel nails anywhere that they are seen. The
siding is available in various types such as
lap, precession cedar shake style, rough sawn
etc…
a. Another siding that we normally use is a
Vinyl product manufactured by the CertainTeed
Corporation. It also comes in many different
types like the Hardi-plank. This product is also
wind rated at 180 MPH and comes with a 10 year
warranty against fading.
8. Mechanical Rough-ins: After the
Windows & Doors are installed, the Roofing has
been installed and the house has been wrapped
with the 30 lb. felt Paper the Mechanical
rough-ins can start.
a. Plumbing always must go first to allow for
the correct flow of the water and sewage. The
Plumber installs all the necessary water and
sewer lines as well as all the rough-in kits for
the Appliances ( dish washers, icemakers etc…)
Toilets, Showers, Sinks and Water heaters.
b. The Heat & Air Conditioning Contractor is
next and he installs all the necessary Duct
work, Thermostat wiring and Line Sets necessary
for the Heat and Air Conditioning system. It is
also his job to install the necessary venting
for the bathroom vents and the dryers.
c. The Electrician is next and he will run miles
of wiring to connect to all the necessary
appliances, light control switches, lighting
fixtures, wall outlets as well as stereo
equipment and security systems.
d. After the 3 contractors above have completed
their rough-in work. Their work as well as all
the framing must be inspected by the local code
officials.
e. After the inspection comes the Insulation.
Here at Alliance we do things a little
different. All the insulation that we use is
Faced Batts. The reason that we prefer this type
is because of it ability to stay where you put
it. It doesn't move around as the wind blows. We
use a full R-30 rated in all our ceilings and
R-9 in all the exterior walls. We also install
R-15 insulation between all our floors and R-11
in all the interior walls for sound proofing.
After all the Insulation is installed it to must
be inspected by the local code officials.
9. Drywall
a. The Drywall is then installed. On all our
ceilings we use a ½" high strength board. This
is nailed as well as screwed to insure no sags.
All the walls are covered with a normal ½"
board, which is also nailed and screwed. In all
our bathrooms and any areas of the home that
might come in contact with moisture we use a
product in the industry know as "Green Board".
This product has a moisture resistant layer on
its outer edge to prevent moisture from
penetrating.
b. Our Drywall is then finished using Sheetrock
Tape and 3 coats of Drywall Mud are applied to
all joints. We also use vinyl rounded corners to
give the edges a unique finish. Some walls are
also finished using the "Knock Down" technique.
Depending on the owner's preference.
10. Painting
a. Next comes the painting. At this point in
the process we have our painter come in and
install a prime coat on all the walls and the
ceiling.
b. He also installs the finish coat on the
ceiling at this time. As a standard we use
either Sherwin-Williams or Devoe brands because
of how well they cover and they are washable.
c. The Painter will come back to the job and
install the final coat after all the trim work
has been completed and the carpet has been
installed.
d. As an added feature for our customers, we
also have our Painter make a final trip to the
job after the furniture has been installed to
fix any imperfections that may have resulted
from "moving in".
11. Trim Work
a. Now the trim crew starts. First they install
all the interior doors. The doors we use come in
several different designs and are manufactured
by JELD-WEN who is a leader in the industry.
b. Next the baseboard is installed. As a
standard we use a "speed base" that is 5 ¼"
high. It helps to give the room a little more
definition.
c. The windows are then trimmed with a 3 ¼" wide
casing.
d. If crown molding is to be installed it is
done at this point. We have installed various
types of crown molding.
e. All the interior and exterior door handles
are installed at this time as well as the door
stops.
f. During this phase of the work, if tile is to
be used in any areas of the house, the backer
board is installed. The board that we use is
known as Durock Brand. It is a cement product
that is used to insure that your tile is
installed on a steady foundation so you don't
have problems with the tiles coming loose at a
later date.
12. Cabinets
a. The cabinets are then installed. We have
several different cabinet manufactures that we
deal with and they work with our customers to
find the right ones to fit the budget.
b. Some cabinet brands that we use are Wood
Mode, Kraft Maid, and Carnell.
13. Appliances
a. Now the Appliances are delivered to the
job. Again we have several vendors that will
work with our customers to insure that they get
the correct appliances for their home. Some
brands of appliances that we work with are Wolf,
Viking, Sub Zero, Maytag, Frigidaire etc…
14. Mechanical Trim Outs
a. At this time all the Sub-contractors come
back in to finish each of their jobs.
b. First the Heat, Vent and Air Conditioning
contractor comes and installs all the outdoor
heat pumps, the interior air handlers, ceiling
or floor vents, return air filters and grills
and the thermostats.
c. Next the Plumber installed all the faucets
for the kitchen sink and all the bathroom sinks,
tubs and showers. He also installs the water
heaters and hooks-up such appliances as the
garbage disposal, and dishwasher. Outside hose
bibs are installed as well. Then all the toilets
are installed.
d. Next is the Electrician who installs all the
wall outlets, switches and light fixtures. He
also hooks-up the Stove, Microwave, dishwasher
and any other major appliances.
15. Floor Coverings
a. Floor covering are then installed.
b. Ceramic Tile is standard in all Alliance
bathrooms, kitchens and entry ways.
c. Due to the fact that most of our homes are
built at the beach we prefer to use wood
laminate products because they are very hard to
scratch. Also real wood flooring is more likely
to separate due to contracting and expanding
from the extreme temperatures that we have.
d. Carpet is normally in the bedrooms.
16. Cleaning Crews
a. The cleaning crews then comes in to do
all the cleaning both inside and out and leave
the house ready for the owners to occupy.
17. Final Inspections.
a. After cleaning the Local Code Officials
are called in to do the final inspections and
give us the Certificate of Occupancy.
b. After this the owners are free to move in and
start enjoying their new home! |